Creagh Concrete, Prestredded factory-Ardboe

OBConstruction were appointed to carry out the building works in the construction of their prestressed flooring factory, Ardboe.  The scope of works included:


Mass Excavation to clear site. (Over 4 acres)

Drainage and services to site and factory.

Foundation works to substructure.

Formation of road ways, parking bays, storage yards and production areas.

New connections to existing services

Placing of concrete yards (approx 4 acres)

Setting of bolt boxes for structural steel sub contractor.

Placing of precast units to external walls.

Reinforced concrete slab to floor of main factory.

Building works to office and canteen accommodation.

Portal framed envelop to receive Kingspan cladding.